 Airport Master PlanManchester • Boston Regional Airport completed its most recent Master Plan Update in 1997. To date, the Airport has completed the majority of the short-term, mid-term and long-term projects contained in the plan. Projects remaining at this time include a nine-gate terminal addition along with the associated apron and taxiways and an additional parking garage. Projects completed include:
| Project | Approximate Cost | Year Completed |
| Runway 6-24 Extension | $31,000,000 | 2001 |
| Relocate Airport Drive | $18,500,000 | 2004 |
| Taxiway E Bridge | $10,000,000 | 2002 |
| Parking Garage | $47,000,000 | 1999 |
| Pedestrian Bridge | $11,000,000 | 2001 |
| Property Acquisitions | $30,000,000 | Ongoing |
| 1998 Terminal Expansion | $16,500,000 | 1999 |
| West End Terminal Expansion | $30,000,000 | 2004 |
| Residential Sound Insulation Program | $33,500,000 | Ongoing |
| Runway 17-35 Reconstruction & Extension | $65,000,000 | 2004 | Other projects the Airport is planning over the next several years include:
| Project | Estimated Cost | Year Planned |
| Runway 06 Reconstruction & Safety Area improvements | $30,000,000 | 2007/8 |
| Glycol Collection/Treatment | $2,000,000 | 2005/6 |
| 3 Gate North End Terminal Expansion | $25,000,000 | 2006/7 |
| Parking Lot G | $2,000,000 | 2005/6 |
| Parking Lot C Expansions | $4,000,000 | 2006/7 |
|